Activity 2: Dissemination and Deployment

Indicative start date: 01/01/2017

Indicative end date: 31/12/2018

Related Milestone(s): 3, 4, 10

The objective of the activity is to disseminate the Action’s results. Three key target groups have been identified for the dissemination activities, each group to be addressed with the help of different tools.

The activity is led by Specure.

Continue reading “Activity 2: Dissemination and Deployment”

Activity 3: Setting-up of European standard for open-data related to QoS of high-speed Internet

Indicative start date: 01/01/2017

Indicative end date: 31/12/2018

Related Milestone(s): 5

The activity is led by CTU

Continue reading “Activity 3: Setting-up of European standard for open-data related to QoS of high-speed Internet”

Activity 4: Developing mobile app for crowdsourcing data

Indicative start date: 01.01.2017

Indicative end date: 31.07.2017

Related Milestone(s): 1

In order to measure the quality of service (QoS) of mobile broadband, a mobile application will be developed, designed for measurements carried out by end users.

The activity is led by Martes Specure.

Continue reading “Activity 4: Developing mobile app for crowdsourcing data”

Activity 5: Developing framework for crowdsourcing data from fixed-line

Indicative start date: 01.01.2017

Indicative end date: 31.07.2017

Related Milestone(s): 2

In order to measure the quality of service (QoS) on landlines, Pilot measurements will use hardware probes in the form of a unique European (Czech) router TURRIS (www.turris.cz/en) that will offer the participating users also other advantages, e.g. in the areas of security and home network protection.

The activity is led by CZ.NIC

Continue reading “Activity 5: Developing framework for crowdsourcing data from fixed-line”

Activity 6: Data publication, aggregation and visualisation

Indicative start date: 01.08.2017

Indicative end date: 31.12.2018

Related Milestone(s): 6,9

The data obtained from the measurements will be made accessible at the levels indicated below. Each one is intended for a different type of user and thus uses different methods and courses of action.

The activity is led by Martes Secure

Continue reading “Activity 6: Data publication, aggregation and visualisation”

Activity 7: Data analysis

Indicative start date: 01.08.2017

Indicative end date: 31.12.2018

Related Milestone(s): 7

The data obtained via crowd sourced measurement will be further analysed for professional use by the telecommunication regulators. These analyses will focus primarily on the following aspects of the quality of service of high-speed Internet.

The activity is led by CTU

Continue reading “Activity 7: Data analysis”